LHD Bucket Design Verification

Finite element displacement contours on an underground loader bucket

K&R Fabrications (South32 Illawarra Coal – Illawarra, New South Wales, Australia)

K&R Fabrications required structural assessment and design verification of an LHD bucket for an underground mining application (South32 Illawarra Coal). Structural analysis and fatigue assessment of the LHD bucket was required in accordance with standard AS 4100 to verify design compliance considering permanent, imposed (bulk material) and QDS attachment/forklift lifting loads as per standard AS/NZS 1170.0 and design parameters provided by K&R Fabrications.

What we did:

Outcome:

Avesta Consulting verified strength and fatigue life of the LHD bucket design and determined appropriate design modifications to achieve minimum service life requirements.